Boundary/fence painting work will start on Monday 5th August and will run through until April next year (2025). 

It should take around three to four days per property to apply two coats of paint with around 120 properties to be completed in this phase.

Please note, no sheds are to be painted during this work and all work is weather permitting. 

All customers and visitors should note any WET PAINT signs displayed in these areas. 

Electrical Works 
Communal area rewiring work will commence on the 27th August starting with Hursthead walk, and will take approximately 3.5 to 4 weeks to complete.

Once complete, the next phase of work will be Skerry Close then Helmshore Walk, which should take approx. 6-8 weeks per block to complete.

Letters have been sent out to all properties directly affected by this phase of works explaining the process and timescales in more detail. Further letters will be released as we approach each batch of works.    

For more information or to check the status of any work to your property please get in touch: send a WhatsApp message to 07500 065 270, email info@s4bmanchester.co.uk, telephone 0300 555 0128 or visit the S4B housing office, 15 Brunswick Street M13 9SU.